To start, click on Tasks on the navigation bar and ensure that your on the Task List View.


1. Selecting multiple tasks

  • You can select multiple tasks by clicking on a white space on each of those tasks. Do not tick the checkbox unless you want to mark that task as "complete". You can also lasso select tasks by clicking on a task and dragging down. This will select all the tasks until you stop the drag.
  • When the tasks are selected, the colour of the tasks will be darker.


Now that you have selected multiple tasks you can do the following:


2. Bulk drag and drop tasks

  • Hover over the left side of the selected tasks and you will see a "multi-direction" icon appear. 
  • Click on this icon and while holding the button down, drag the group of tasks where you want to move them to. 
  • Release the button to drop the tasks at their new position.


3. Bulk Edit tasks

  • Select all the tasks you wish to edit at the same. 
  • Hover over the "Bulk Actions" dropdown menu at the top of the screen.
  • You will see several options Bulk Action Options on this menu.
  • Select the "Edit" option.
  • A "Bulk Task Edit" screen will open on your screen. 
  • Make the changes where relevant. e.g. Bulk adding an owner to all the tasks.
  • Save to save the changes to all the tasks you selected.


    Bulk editing tasks options


4. Bulk Add Owners to tasks

  • Select all the tasks you wish to edit at the same time.
  • Hover over the "Bulk Actions" dropdown menu at the top of the screen.
  • You will see several Bulk Action options on this menu.
  • Select the "Edit" option.
  • A "Bulk Task Edit" screen will open on your screen.
  • Select the task Owner.
  • Save. All the tasks you selected will now have that Owner.


5. Bulk adjust dates

  • Select all of the tasks that you wish to adjust dates for at the same time
  • Hover over the "Bulk Actions" dropdown menu at the top of the screen.
  • You will see several Bulk Action options on this menu.
  • Select the "Adjust Dates" option
  • Input the the amount of days you would like to adjust task dates by. You can input the amount of calendar days or choose a date from the calendar which will auto calculate the number of calendar days for you.
  • Click "Adjust"
  • All of your task start and end dates will be adjusted accordingly.


6. Bulk comment on tasks

  • Select all of the tasks that you wish to comment on at the same time
  • Hover over the "Bulk Actions" dropdown menu at the top of the screen.
  • You will see several Bulk Action options on this menu.
  • Select the "Comment" option
  • Enter your comment. (you can also upload a file or change the comment watchers)
  • If you'd like to copy the comment to the job/opportunity select the "Copy comment/attachments to their Job" checkbox
  • Save.
  • Your comment will be added to all of the tasks selected in the first step.


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article